North Terminals Project

  • Scope: Quality Control Assurance, Scheduling, Document Control
  • Location: Los Angeles, CA
  • Client: Los Angeles World Airports
  • Budget: $130 Million
  • Timeline: 2010

On April 16, 2007, the Los Angeles World Airports (LAWA) awarded a contract to the team of Swinerton Builders, JGM, and Siemens based upon a best-value proposal process for the conversion of the existing lobby-based checked baggage screening equipment at Terminals 1 through 3 at the Los Angeles International Airport to automated equipment that will integrate EDS screening equipment into each terminal’s baggage conveyor sortation system.

To avoid passenger or airline operations disruption and to manage multiple tenants’ inbound/outbound flight schedules, JGM provided construction management services for 34 construction phases, 42 baggage handling system phases, 10 baggage handling cutover phases, and over 30 electrical system shutdowns. The project included the installation of a new baggage control system, system testing, a new 480 KV bus duct, an HVAC system, plumbing, steel frame canopies, and retaining walls.

JGM was responsible for developing the project schedule and integrating the work of all contractors into the 116 phases of the project as defined by LAWA. JGM also created and implemented the Contractor’s Quality Control program, which consisted of three specific phases of control for each definable feature of work: preparatory, initial or Startup, and Follow-up. JGM staff prepared 3D coordination drawings that integrated the baggage handling system with the construction elements of the existing and new structures.